Red River Valley Water Supply Project

Contact Us »

Near Carrington, construction crews have kicked off the 2023 construction season on the Red River Valley Water Supply Project (RRVWSP), focusing on the 72” transmission pipeline in Foster County that will eventually span from the McClusky Canal to the Sheyenne River.

In May, the construction crew began prepping the right-of way for the remaining stretch of pipeline falling under the nine-mile construction contract started in 2022. The work consisted of removing topsoil, dewatering, and setting up equipment. Pipe installation began in early June. Contractors are scheduled to wrap up substantial completion by the end of November 2023.
 
The discharge structure, where the water will enter the Sheyenne River, was completed in 2022. It is located about six miles south of Cooperstown. The Missouri River Intake, four miles south of Washburn, is also now complete. Final restoration of the site is currently underway.